The City Engineer’s Office will upgrade traffic signals at First Avenue and Mill Road this week.
Beginning Monday, March 8 through Wednesday, March 10, the traffic signal at the intersection will be out of service as crews perform necessary work.
During that time, the intersection will operate as a four-way stop.
Motorists and pedestrians should consider alternative routes, if possible.
The upgrade is part of a city-wide project to modernize nine traffic signals.
Center curb mounted pedestrian signals, which are frequently damaged, will be relocated to new overhead spans.
Overhead microwave vehicle detection and countdown-type pedestrian signals will also be installed.
Material furnished by City of Evansville